Concrete Calculator: Volume, Cement Bags, Sand & Aggregate

Calculate concrete volume for a slab, beam, footing or column, with cement bags, sand and aggregate for M10, M15 and M20 nominal mixes.

Element
Shape
ft
ft
in

A typical house roof slab is 5 inches.

Mix

For M25 and above, use a design mix from your engineer or ready-mix supplier.

%

Spillage and uneven surfaces. 2–5% is typical.

Assumptions used EDIT ▾

Commonly 1.52–1.57.

Wet volume = length × width × depth (or π r² h). Dry volume = wet volume × the dry factor, because the dry ingredients shrink when mixed with water. Materials are split in the chosen ratio; cement is converted at 1,440 kg/m³ and 50 kg per bag. Nominal-mix quantities are an estimating convention; a design mix will specify its own proportions.

CONCRETE VOLUME

1.46m³

52 cft · includes 3% extra. Order about 1.5 m³ of ready-mix.

Cement11.8 × 50 kg
12 bags
Sand0.61 m³
22 cft
Aggregate (20 mm)1.22 m³
43 cft
Before wastage
1.42 m³
Concrete volume1.46 m³

How it’s calculated

Dry volume = wet volume × 1.54; cement = dry × 1 ÷ (1 + sand + aggregate) × 1440 ÷ 50 bags

Example: 1 m³ of M20 (1:1.5:3): dry 1.54 m³ → cement 0.28 m³ ≈ 8.1 bags.

Questions

Why multiply by 1.54?+

Dry cement, sand and aggregate shrink in volume once water is added and the concrete is compacted. 1.52–1.57 is the usual allowance.

Can I use nominal mix for M25?+

Nominal mixes are used up to M20. For M25 and above use a design mix.

Estimates for planning, based on the assumptions shown. They are not a guarantee of quantities or professional engineering advice; check critical work with a qualified professional.