On a construction project the same numbers pass through several documents. Mixing them up leads to disputes: an owner treats an estimate as a price, or a contractor prices a BOQ that was never complete.

At a glance

Estimate BOQ (bill of quantities) Quotation
Question it answers Roughly what will this cost? Exactly what work, in what quantity? What will you charge me?
Usually prepared by Engineer, architect or owner Engineer or quantity surveyor Contractor or supplier
Contains Approximate quantities and rates Itemised quantities with units; rates left blank for bidders Items, rates, totals, taxes and terms
Binding? No Defines scope when part of a contract An offer that becomes binding when accepted
Stage Planning and budgeting Tendering Before award or purchase

Estimate

An estimate is a forecast. A preliminary estimate might use a cost per square foot; a detailed estimate measures each item of work and applies current rates. Either way, it helps the owner decide whether the project is affordable and sets a budget. Rates and quantities will change as the design develops.

Bill of quantities

A BOQ lists every item of work with a clear description, unit and measured quantity: for example, "brickwork in 1:6 cement mortar in superstructure, 230 mm thick — 42.5 m³". Bidders fill in their rates against the same quantities, so their prices can be compared line by line. A BOQ is only as good as its measurement and descriptions; missing items become disputes and variations later.

Quotation

A quotation is a contractor's or supplier's priced offer. It should state what is included and excluded, rates, taxes, validity period, payment terms and timelines. Once the customer accepts it (ideally in writing), it becomes the basis of the agreement.

How they connect

  1. The owner or engineer prepares an estimate to set the budget.
  2. For tendering, the engineer prepares a BOQ from the drawings.
  3. Contractors return quotations, often by pricing the BOQ.
  4. The accepted quotation, with the BOQ and drawings, forms the contract.

Good practice

  • Write units and item descriptions precisely; "plaster" is not an item, "12 mm cement plaster 1:6 on internal walls" is.
  • Keep a quotation's validity short when material prices are moving.
  • Record accepted changes in writing as variations to the quotation.

Tools

Quantities for a BOQ come from calculations like concrete and brickwork. Tradespeople can send a clean priced offer with the free quotation tool.